After on-and-off lockdowns which have caused more slowdowns in school progress, we have recently returned to full-speed construction. The first floor of the school is being built in five sections. Section 1 has finished roof and pillars and walls are underway.
The fifth section has finished pillars and the next step will be constructing the roof. The Second, third and fourth sections have finished elevations except for the final layer of concrete, after which pillars will be constructed.